ledgewood tennis - b4.JPG
You might recall how bad the courts have looked over the past couple of years.

ledgewood tennis - b4 2.JPG
We had mossy spots.

ledgewood tennis - b4 3.JPG
We had wet spots.

ledgewood tennis - b4 4.JPG
We had muddy spots.

ledgewood tennis - b4 5.JPG
We had a mess.

ledgewood tennis - crew on site 4-14-10.JPG
NGI is replacing the courts.

ledgewood tennis - crew on site 4-14-10 2.JPG
They unloaded all manner of equipment for the job.

ledgewood tennis - crew on site 4-14-10 x Dave John Junior.JPG
Dave John and Junior are on the repair crew.

legdgewood tennis - Jeremiah cleans up 4-11.JPG
First step was having Jeremiah clean up. The orange marks low spots or dead spots.

legdgewood tennis - keith john junior scrape mold dirt4-11.JPG
Here, Keith, John and Junior scrape mold and dirt.

legdgewood tennis - ray and junior discuss low spots 4-11.JPG
Ray and Junior discuss low spots.

legdgewood tennis - Jeremiah loading 4-11.JPG
Jeremiah unloading supplies.

ledgewood tennis - junior sprays sealant.JPG
Junior sprayed sealant.

ledgewood tennis - junior sprays sealant john helps.JPG
Junior sprayed sealant while John helped.

ledgewood tennis - junior sprays sealant john helps2.JPG
Junior sprayed sealant while John helped.

ledgewood tennis - junior sprays sealant john helps sand.JPG
Junior sprayed sealant while John helps with the sanding.

ledgewood tennis - junior sprays sealant john helps sand2.JPG
Junior sprayed sealant while John helps with the sanding.

ledgewood tennis- removing fence 4-21-10.JPG
Next step was removing fence so the big rolls of carpet could be brought in.

ledgewood tennis- john rolls sand 4-21-10.JPG
Here, John rolls sand for leveling.

ledgewood tennis- john rolls sand 4-21-10 2.JPG
John rolls sand for leveling.

ledgewood tennis- junior jerimiah level 4-21-10.JPG
Junior and Jeremiah work to level low spots.

ledgewood tennis- junior jerimiah level 4-21-10 2.JPG
Junior and Jeremiah work to level low spots.

ledgewood tennis- john rolls sand 4-21-10 3.JPG
With low spots leveled, the area was compacted.

ledgewood tennis- the delivery truck 4-21-10.JPG
A large delivery truck brought in materials.

Ledgewood courts 4-26-10.JPG
The Ledgewood courts got heavy rain on 4-26-10.

Ledgewood courts2 4-26-10.JPG
The Ledgewood courts got heavy rain on 4-26-10.

ledgewood tennis - carpet unrolls 4-27-10.JPG
The Ledgewood courts got heavy rain on 4-26-10.

ledgewood tennis - carpet unrolls 4-27-10 2.JPG
The first of the new carpet was unrolled 4-27-10.

ledgewood tennis - carpet unrolls 4-27-10 3.JPG
The Ledgewood tennis courts already look brighter.

ledgewood tennis - carpet unrolls 4-27-10 4.JPG
Sand makes the lines look wavy as the carpet is installed. Added sand covers the lines during installation.

ledgewood tennis - carpet unrolls 4-27-10 5.JPG
Added sand covers the lines during installation.

ledgewood tennis - carpet unrolls 4-28 -2.JPG
The back court area will be unrolled at a 90 degree angle to the main surface.

ledgewood tennis - carpet unrolls 4-28.JPG
Later, the sections are fused.

ledgewood tennis - margie harler denise coniam inspect.JPG
Margie Harler and Denise Coniam inspect the job.

ledgewood tennis - margie harler denise coniam inspect2.JPG
Denise Coniam pinpoints a former dead spot while Margie Harler checks the spot.

ledgewood tennis - crew break 4-28.JPG
It's all hard work...interrupted only by lunch.