Grace House of Hope, an orphanage for 30+ girls in Haiti was built on top of an existing church in 2008 with funds from Impact for Jesus. The church and orphanage collapsed Jan 12, 2010 in the devastating earthquake. Thanks be to God that no one was injured in this collapse. The orphanage was rebuilt in 2010 with finishing touches completed in 2011. Thanks to all of our donors and work teams! We couldn't have done any of it without YOU!

Original Church Building
The original building. A second story was added as an orphange.

At Work
Everything is done by hand in Haiti

Second Story Partially Completed
The second story orphanage is taking shape

Boots
Old inner tubes are used to protect his feet. Nothing goes to waste in Haiti.

Second Story Nearly Complete
Roof is on and nearing completion

Cross
Three crosses were added to the peaks of the roof

Pouring the Roof
Putting concrete on the roof--one bucket at a time. The project took all day and about 50 Haitian workers who worked without stopping from dawn to dusk.

Working on the Roof
One bucket at a time.

Working on the Roof

Second Story Complete
The orphanage is ready!

All the Children
All the orphaned girls gathered on the balcony! Home Sweet Home!

Lighted Cross
The completed orphanage at night--the cross is lit with a 12 volt battery at night (no electricity most of the time)

The Outside is Painted
Finishing work continues after everyone moves in.

Earthquake--Collapsed Building
On Jan 12, 2010, a devastating earthquake hits Haiti. The church and orphanage collapsed.

Tearing it Down, Breaking it UP
Two weeks after the earquake Impact for Jesus was on site working with Haitian laborers to clear the rubble so rebuilding could begin.

Labor of Love
After the men sang How Great Thou Art the sledge hammers began and the remainder of the building was turned to dust and rubble.

Breaking it to Pieces
Destruction continues

Rebar and Dust
Not much left of the building--skeleton of rebar

Lots of Work to Go
The building is almost down but there is still the first floor and foundation to get through

Some Bigger Pieces
No heavy equipment here--just strong willed Haitian's wanting to work and to rebuild

The Skeleton
The concrete walls and roof are gone

A Difficult Piece of Rebar
One last peice of rebar to go before the roof and walls are gone

Orphanage is Gone-Church Rubble to be Cleared
The orphanage is gone. The first story church is still below what was the floor of the orphanage/the roof of the church

The Floor of the Second Story Orphanage
Much more work to break through the floor

Surveying the Damage of the Foundation
The entire foundation is dug up and replaced to assure a safe building is rebuilt

Footing Hole
Holes are dug for the footingss to be replaced

More Footings Replaced
One man and his family work on the foundation and footings

Dog by Hand
All of this work continues by hand. No front end loaders no trenchers here

Temporary Church in Background
Two Impact for Jesus teams built a temporary church structure for worship durring construction

Floor and Foundation Set
Ready to pour the floor of the orphanage

Ready for the Pour
Impact for Jesus not only funded the project but several teams help in the building process--although the real labor was done by the Haitians.

Load of Sand
Supplies arrive

The Team Prepares
Getting ready for the work to begin

Impact for Jesus Team on Site
Our team spent the week working side by side with the Haitians--they were better workers then we were!

Concrete-Water-Sand
The pour begins as everything is in place

Impact for Jesus Consulting
Chris from Impact for Jesus consults with the general contractor over the final details

Longest Day
A long day of pouring concrete--bucket by bucket--wheelbarrow by wheelbarrow

Completed Pour
The floor is poured

Rene from Impact for Jesus
Rene from Impact for Jesus surveys the new floor

Rene Observes the Work
Rene observes the work and reports back to our US friends

Forms for Cloumns
The forms are readied to accept the concrete to form the columns to support the roof

Columns Rise
Forming for another pour

The Forms Stand Tall
The wodden forms are plumbed

Forms
Work continues

Forms for Columns Plumb?
Near ready for the concrete

Ready for Concrete
Some forms are ready to be filled with concrete

Haitian Classroom
One of the classrooms for the school kids while work continues on the orphanage

Final Ajustments
Final ajustments are made just before the concrete is poured

The New Orphanage Building
The building needs some work but the roof is on and the walls are up. Finish work needs to be done.

The New Building
Building is nearly complete

Another View
View of the building from the roof of the school

Inside Finish Work
Finsh work being completed on the inside of the building

Finish Work on Outside is Complete
Finished walls on the outside of the new orphanage

Inside Near Completion
The inside is painted and finished--the girls moved in the next day

Completed Building
Finsh work continues on the building but the girls have moved in and the work never ends.

Front of Building
The building is painted inside and out