Construction Progress

A NEW BEGINNING

We are very proud to announce that Pinellas County issued the Certificate of Occupancy for The Inn on the Pond on February 29, 2012.  The subcontractors have moved out and the new owners have moved in.  Menorah Manor is busy getting their new building ready for their new residents, who should start arriving any day now.

Creative Contractors, Inc. thanks you for following our progress over the past thirteen months as we completed the construction of The Inn on the Pond.  If you would like to see examples of other project by Creative Contractors, Inc., please select our link below.

THE FINISH LINE IS IN SIGHT

A little over a year ago we broke ground and started the groundwork required to support what is now “The Inn on the Pond”.  We started planning the progress by month, then by week, and now we are down to days.  The excitement to finish “our” building is unmistakable.

The exterior changes over the last month make for an eye-popping site as you approach the entrance.  Valley Crest Landscape Development has worked diligently to plant thousands of plants and trees to maintain the natural beauty of the pond and nature preserve.  Gilbert & Byrd is putting the last of the stone in place on the building and B.R.W. Contracting will be laying the final lift of asphalt and striping the parking lot within the next few days.

Inside the building Creative Contractors is pulling off the protective coverings in the resident rooms and Sunshine Services of Central Florida is cleaning each room in preparation for turning the building over to Menorah Manor at the end of February.  All other subcontractors are working diligently putting on the finishing touches throughout the rest of the building - light fixtures are being installed, flooring is being laid, the last walls are being painted, air conditioning is being checked, and the final touches are being put in place. 

This time next month we will be presenting a final update on the project.  All inspections will be complete and Menorah Manor will have taken occupancy.  Everything will be ready for the new residents of “The Inn on the Pond”.

IT LOOKS LIKE "SPRING CLEANING" AROUND HERE

“Spring Cleaning” has started early at The Inn on the Pond.  As we come down to the last few weeks of construction and we complete portions of the building, we are moving materials around and cleaning up behind us as we move to the next section.  Storage space is at a premium, but materials keep coming.  They are temporarily stored wherever we can find a spot.  As you look through the photos, you may still notice stacks of building materials, as well as what looks to be a whole lot of paper and plastic over the floors, counters, fixtures, etc.  They may not make for a pretty picture, but they do make for a beautiful end product as they protect the new finishes from scratches, dents, paint splatters, etc.  Please be patient – the protective coverings will be coming off and everything will be organized and in its proper place very soon.

 

The first thing you may notice as you approach the building is that all scaffolding has been removed.  The exterior stucco and painting are finished and the building is ready for the decorative stone to be set in place in January.  If you make it around to the back of the building, you will see we have some landscaping in place!  ValleyCrest had to plant the large trees prior to pouring the concrete for the Promenade to prevent the heavy equipment from damaging and breaking up the concrete once it was in place.  Once the trees were planted, Gilbert & Byrd began prepping and pouring the concrete.  At the same time, B.R.W. was busy on the south side of the property laying the first lift of asphalt and installing the curbs for the south parking lot.

 

As you enter the building you will once again notice that all scaffolding has been removed.  The majority of the overhead mechanical, electrical, plumbing, and fire protection is complete and most of the drywall is in place and finished.  The residential units on the first floor of the two towers are basically finished and “locked down” to prevent unnecessary traffic in and out of the rooms, thereby preventing potential damage to the finishes.  As each floor is finished it will be closed off to traffic and ready and waiting for the cleaning crew to come in at the end of the project.  As the residential towers are completed the subcontractors are moving to the rest of the building to finish their scopes of work.  There is still a lot of work to get done in the non-resident areas (Kitchen, Assembly, Multipurpose Room, etc.) to have the building ready for the final inspections and issuance of certificate of occupancy in February. 

 

There is still a lot of activity that has to take place throughout the month of January.  But, in the not-to-distant future, the construction will be finished, equipment will be tested and tweaked, the cleaners will have made their way through the building, all the landscaping will be planted and growing, and the last stripe will be painted on the parking lot.  It will be time to turn the keys over to the new owners.

Look At All That Activity

The end of the project is fast approaching and you can feel the excitement building as a whole new group of subcontractors comes in to complete the project and turn over a beautiful building for the future residents.  Now that the initial trades have completed the majority of the electrical, HVAC, plumbing, and drywall layout and installation, the finishing subcontractors have moved into the interior of the building.  You can see the progression as the subcontractors complete one floor and move on to the next.  Southern Quality is installing the interior doors, Trio Plus Painting is applying the finish coatings of paint, Bay Area Commercial Interiors is installing ceramic tile on the bathroom walls and floors, J & E Custom Cabinets is installing cabinetry, and APG is installing the light fixtures.  There is a lot of coordination taking place right now to make sure that so many trades keep on schedule and don’t run over each other.

Major changes are taking place around the exterior of the building also.  KHS&S has completed all stucco work and Trio Plus Painting has finished the exterior painting.  Soon you will see Gilbert & Byrd setting the decorative stone at the front of the building.  Curtis Pools was on site and poured the swimming pool, while behind the scenes the project team was selecting the final finishes for the pool and deck.  The team has also been meeting with Valley Crest to finalize the landscaping details so that all trees and plants compliment the architecture of the building and provide a beautiful, relaxing environment for residents. 

Activity around the site is constantly increasing as we approach our finish date and things are changing on a daily basis.  Next month you will be able to see a much clearer picture of what the end result will be.  Please check back then.

Construction Update

Things move quickly at this stage of the project.  The exterior stucco and painting is almost complete, Pinnacle Door has installed all the exterior doors, and Countryside Glass has installed the windows.  Ramcon has started laying shingles, so the roof should be finished soon.  And if you notice a big hole in front of the building when you drive by, it’s because Curtis Pools has started digging the pool near the entrance to the building.

Activity has really picked up on the interior of the building now.  Bayshore Plumbing, Blume Mechanical, APG Electric, and St. Petersburg Fire Protection continue moving from floor to floor roughing in the mechanical, electrical, and fire protection conduit and piping ahead of drywall for the walls and ceilings being installed by KHS&S Contractors.  Work has progressed enough on the first floors of the building so that Trio Plus Painting is painting rooms, J & E Cabinets is installing cabinets, and Bay Area Commercial Interiors is laying tile in the bathrooms.  In the Kitchen the range hoods have been installed, the ceiling is going in, and the epoxy floor will be set early in November in preparation of all the kitchen equipment and washers and dryers being installed at the end of November. 

Next month will see a steady progression from floor to floor of all the trades and the exterior of the building should be complete.  As soon as approval comes from the Pinellas County Building Department, site work for the Promenade that will overlook the Pond in back will commence.  The Project Team has already started looking at the landscaping and the pool finishes that will complete the exterior appearance of the building.  What a long way we’ve come in just a few short months!

September 2011 Update

A number of visual changes have occurred on site this month.  If you happen to drive down Greenbriar Boulevard, you will immediately notice the addition of color to the exterior of the building.  KHS&S has completed the stucco application to Memory Care and Trio Plus Painting followed right behind to complete the painting.  Both subcontractors are now working on completing the exterior of the Residence Units.  You will also notice that we now have windows and exterior doors installed in all areas of the building.  Countryside Glass & Mirror and Southern Quality have worked diligently to install the doors and windows so we have a watertight building.  We also had cranes back on site this month as APG Electric installed the generator and Blume Mechanical installed the cooling towers in the Mechanical Yard.

Now that we are watertight, our subcontractors have jumped in and are moving right along on the interior of the building.  KHS&S has completed the drywall on the first floor of Memory Care and has moved over to the first floor of the Residence Units.  From there they will move to the Kitchen area so all prep work can be complete for delivery of the kitchen equipment at the end of November.  As always, Blume Mechanical, APG Electric, Bayshore Plumbing, and St. Petersburg Fire are working quickly to stay ahead of the drywall subcontractor and have the next area ready so they don’t have to wait.  Our subcontractors are doing a fantastic job of coordinating each step.

The most talked about story of the month, though, is the successful completion of the Model Apartments.  After much hard work and long hours to complete the interior finishes on one unit in Memory Care and one unit in the Residential Area, Creative Contractors turned the Model Apartments over to Menorah Manor Senior Living.  They quickly started moving in furniture and decorating the Apartments so possible tenants will have an opportunity to view what their future home may look like. Please take a minute to view the photos.  

August 2011 Update

Tremendous changes to the exterior of the buildings have taken place the month of August.  Trusses have been installed on all sections and all lightweight concrete roofing is complete as we move ever closer to a dried-in building.  KHS&S Contractors started applying the stucco finish to the exterior of Memory Care mid-August. Southern Quality also began installing doors and the last week in August room window installation in Memory Care and storefront windows in Assembly was underway by Countryside Glass & Mirror.  The roof, stucco, windows, and doors will form a system to keep moisture from penetrating to the interior of the building.  The most noticeable change to the building is the paint.  After the stucco finish dried and colors were approved by the design team, Trio Plus Painting began painting the exterior of Memory Care.  Throughout the month of September they will follow the stucco applicator from area to area until all sections are complete and it looks like one complete building – Inn on the Pond.

All trades are maintaining a steady pace on the building interior.  KHS&S continues with room layout and framing; Blume Mechanical, Bayshore Plumbing, and APG electric progressively move forward with the mechanical, plumbing and electrical layouts on all floors; and St. Petersburg Fire is hanging pipe throughout all sections.  Pinellas County inspectors have been on site daily to verify that all work meets building codes.  Everyone on site is working together to meet our target date of September 1 for complete dry-in so we can start hanging drywall in the first floor rooms of Memory Care.

Behind the scenes, Creative Contractors has been working with Menorah Manor Senior Living and Besselo Design Group to finalize the interior finishes.  These are critical decisions that must be completed so that the major event of September stays on schedule:  the opening of the completed Mock-Up Room for viewing.  In manufacturing and design, a mock-up is a scale or full-size model of a design or device used for teaching, demonstration, design evaluation, or promotion.  In this instance, the Mock-Up Room will be full size model of a one-bedroom unit for possible future tenants to view. There will be more information regarding the Mock-Up Room in September's update.

Moving Closer to Dry-In

The month of July saw the team working ever so much closer to the critical milestone of a dried-in building.  The roof deck on Memory Care is in place and the metal trusses are being set.   Window sills are in and temporary plastic covers the windows until permanent windows are delivered in August. You can also see scaffolding around Memory Care as KHS&S prepares to start spraying stucco.  Interior room layout and mechanical, electrical, plumbing, and fire sprinkler rough-in is basically complete on first floor and our subcontractors are making steady progress on the second and third floors.  All is on target in anticipation of the start of drywall installation. 

Gilbert and Byrd has completed the third floor block in the Residence units and the building is ready for the hollow core floor planks to be set by Coreslab the first week in August.  Blume Mechanical, APG Electric, Bayshore Plumbing, and St. Petersburg Fire also have crews working rough-in on all three floors of the Residence units and KHS&S is progressing with interior framing and wall layout.

The Multi-Purpose/Kitchen and Administration buildings and the lightweight concrete roof insulation is in place.  The lightweight concrete process includes installation of styrofoam over a thin layer of concrete followed by a layer of concrete poured over the styrofoam.  Lightweight concrete insulation is an economical, long-term solution to protect your buildings from water intrusion.  The roofs in these areas are ready for setting the trusses in early August

Creative Contractors, Inc., along with Bessolo Design Group and Menorah Manor, is continuing with the submittal review process for interior finishes – paint, flooring, ceiling, and cabinetry.  There is also an increase in on-site coordination meetings between Creative Contractors, Architect, and Owner to ensure any changes to enhance the design and maintenance of the facility are addressed quickly and forwarded to the subcontractors in a timely manner to keep the project on schedule.

Lastly, in keeping with a long-standing tradition in the construction field, on July 21 Creative Contractors provided a topping-out party for our subcontractors who have worked so diligently to get us to roof level.  The subcontractors, along with representatives from Menorah Manor and Bessolo Design Group, enjoyed lunch from Wing House.  Creative Contractors thanks everyone for their hard work and dedication to keeping this project on schedule.

Building Progress

June was another busy month as our subcontractors worked steadily toward the goal of completing the placement of the hollow core floor plank, concrete block walls, and mechanical, electrical, and plumbing rough-in as quickly as possible to get the buildings under roof.  Our masonry subcontractor, Gilbert & Byrd, continued the concrete block walls for the 3rd floor of Memory Care along with the first and second floors of the Residence units.  They also provided the concrete floor topping after Coreslab Structures placed the hollow core planks for each floor.  KHS&S Contracting, our metal framing subcontractor, continued with the framing of the interior partition walls and Blume Mechanical, Bayshore Plumbing and APG Electric continued with the installation of the overhead piping and conduit and wall rough-in work.

 

Behind the scenes, Creative Contractors continued the buy-out and submittal approval of the interior finishes.  They also continued to conduct on-going coordination meetings between Menorah Manor Senior Living, Creative Contractors, Besselo Design Group, and the subcontractors working on the project.  Besides the excellent coordination of the subcontractors in the field, these meeting are critical to insuring the project stays on schedule and that any questions and issues are addressed and resolved quickly so as not to delay any portion of the work.

 

Creative Contractors also selected a LEED Consultant for the project and held their first meeting with the Consultant and the Design Team.  For those that do not know, LEED stands for Leadership in Energy and Environmental Design.  Menorah Manor has committed to incorporating the principles of “green” building into the design and building of The Inn on the Pond.  Creative Contractors is acknowledged as a leader in green building construction and has registered The Inn on the Pond project as a LEED certified facility.  There will be more updates about LEED as the key components of  LEED certification are incorporated into the building process.

 

Next month will see increased activity on site with the delivery and installation of exterior windows and commencement of roof truss installation and roofing dry-in activity.  More subcontractors will be brought on board and we will start more interior work as the buildings become water tight. 

May 2011 Update

The month of May has been busy and the building seems to rise on a daily basis.  The exterior block walls, concrete columns, and structural beams that make up the support of the precast floors are on the rise.  Behind us is the completion of all the underground piping and conduits that were needed to be completed for the 1st floor slab.

After completion of the first floor block work for Memory Care (Section A) and the Bedroom Units (Section B), the hollow core planks are set.  A hollow core plank is a precast slab of pre-stressed concrete that has tubular voids extending the full length of the slab.  The slabs are cut to the length required for the building and shipped to the job site where a crane carefully swings the planks from the truck to the deck and each plank is set in place.  After the hollow core planks are set and grouted, a concrete topping is poured over the planks forming the floor for the second story.  Gilbert and Byrd, the masonry and concrete subcontractor, can then continue laying the block walls for the next floor level.  At the same time, Blume Mechanical, APG Electric, and Bayshore Plumbing start the MEP rough-in on the second floor. KHS&S Framing & Drywall Company can also now begin metal frame layout of the interior walls on the lower floors.

It is now quite easy to see the buildings taking shape for Memory Care and the Bedroom Units.  You can also see the Multi-Purpose / Kitchen (Section D) and Administration (Section E) Buildings starting to take shape.  If you have been following the progression of the first two buildings, you can see that these two buildings are following the same path.    Layout, MEP rough-in and slab are complete.  Gilbert & Byrd is laying first floor block on Multi-Purpose/Kitchen and will move over to Administration next.

Next month the masonry walls and the setting of the hollow core planks should be coming to completion and we will be preparing for the next step, which is preparing for roof activities and working inside the buildings on the interior room partition walls.

April 2011 Update

The month of April has had a flurry of activity throughout the site, but the most notable changes can be seen in Section “A” (Memory Care) and Section “B” (Bedroom Units).  The month started out with a big push to get the slab in Memory Care prepped and ready for the concrete pour on April 7.  The concrete trucks started arriving at 7:30 a.m. and in about three hours Gilbert and Byrd had poured and spread 180 yards of concrete.  Following closely behind were the finishers to insure that by the end of day the concrete had a smooth, level finish and was ready for the next set of crews to come in and start vertical construction.  In the meantime, another set of crews was busy in the Living Units doing all the ground work to prepare for its slab pour on April 22.

Right behind the Memory Care slab pour, United Drilling was on site to drill the elevator pits on April 8.  They were able to drill and cap all three 30’ holes in one day - a great way to end the week.

While all this activity was going on, other crews were busy working in the Assembly and Multi-Purpose / Kitchen areas.  Gilbert and Byrd was completing layout, excavation and pouring of the concrete foundations.  Blume Mechanical, APG Electric, and Bayshore Plumbing were working to get underground piping and conduit in place.  All activity was geared toward getting the slabs for these two areas poured next month.

At the job site office Creative Contractors has been reviewing shop drawings and product submittals and forwarding them to the Architect for review.  This is also a busy time working towards completion of the subcontractor buy-out process and coordinating Owner Direct Purchase Orders with vendors.  

One of the most critical factors of the construction right now is coordination with each of the major trades.  Creative has been diligently meeting with the subcontractors, architect, engineers, and owner to resolve any possible issues that may affect construction down the road.  While this is an on-going process for the Construction Manager throughout construction, good coordination practices up front will lead to a successful completion of the project.

As we continue to complete the slabs-on-grade in May, you can look forward to seeing progress on the upper floor levels.  Keep watching.

March 2011 Update

Things are looking up at The Inn on the Pond these days.  As in, no longer do you look out across the site and see an expanse of dirt.  As promised, the walls are starting to rise. 

Gilbert & Byrd is on site focusing on layout and pouring of the building foundations and foundation walls for Sections A and B.  The foundation walls and slabs for elevators 2 & 3 have been completed and our next big event is pouring the slab in Section A (Memory Care units).  The concrete trucks are regular visitors to the site these days. 

Our subcontractor team continues to grow as our mechanical, plumbing, and electrical underground piping and conduit are put in place.  The site lift station has been installed and underground utility work continues.

April will be busy with concrete foundations, concrete slab pours, masonry walls, and underground piping for buildings.  By the end of the month the footprint of the building will be in place.

There is much activity on the site these days, so stay tuned for regular updates.

January 2011: New Year Leads to a New Start

January 2011 was an exciting month for the Inn on the Pond team.  After nearly three years of development, planning, and patience, work on the project has begun.  Although it may not look like much, Creative Contractors and the sitework subcontractor have been preparing the soil to cultivate for the long held dream to build Inn on the Pond. 

 

Just like the dream that was the seed planted in the hopes of Menorah Manor many years ago, Creative Contractors has been planting the seeds for a great new project by mobilizing our onsite staff and bringing subcontractor team members on board.  The foundations will begin to grow, the concrete trucks will roll, and soon the walls will rise... 

 

Stay tuned!!!  We are just getting started... 

 


Favorite links

The Inn on the Pond
Creative Contractors Inc.
Bessolo Design Group

Aerial Photos

Aerial Photos

Menorah Manor 1-14-11 03.jpg
Menorah Manor 1-14-11 03.jpg
Menorah Manor 1-14-11 03.jpg 2011-01-14
Menorah Manor 2-14-11 01.jpg
Menorah Manor 2-14-11 01.jpg
Menorah Manor 2-14-11 01.jpg 2011-02-14
Menorah Manor 3-15-11 01.jpg
Menorah Manor 3-15-11 01.jpg
Menorah Manor 3-15-11 01.jpg 2011-03-15
Menorah Manor 4-15-11 001.jpg
Menorah Manor 4-15-11 001.jpg
Menorah Manor 4-15-11 001.jpg 2011-04-15
Menorah Manor 5-16-11 03.jpg
Menorah Manor 5-16-11 03.jpg
Menorah Manor 5-16-11 03.jpg 2011-05-16
Menorah Manor 6-15-11 03.jpg
Menorah Manor 6-15-11 03.jpg
Menorah Manor 6-15-11 03.jpg 2011-06-15
Menorah Manor 7-15-11 02.jpg
Menorah Manor 7-15-11 02.jpg
Menorah Manor 7-15-11 02.jpg 2011-07-15
Menorah Manor 8-16-11 02.jpg
Menorah Manor 8-16-11 02.jpg
Menorah Manor 8-16-11 02.jpg 2011-08-16
Menorah Manor 9-13-11 01.jpg
Menorah Manor 9-13-11 01.jpg
Menorah Manor 9-13-11 01.jpg 2011-09-13
Menorah Manor 10-12-11 02.jpg
Menorah Manor 10-12-11 02.jpg
Menorah Manor 10-12-11 02.jpg 2011-10-12
Menorah Manor 11-16-11 03.jpg
Menorah Manor 11-16-11 03.jpg
Menorah Manor 11-16-11 03.jpg 2011-11-16
Menorah Manor 12-14-11 02.jpg
Menorah Manor 12-14-11 02.jpg
Menorah Manor 12-14-11 02.jpg 2011-12-14
Menorah Manor 1-16-12 02.jpg
Menorah Manor 1-16-12 02.jpg
Menorah Manor 1-16-12 02.jpg 2012-01-16
Menorah Manor 2-15-12 03.jpg
Menorah Manor 2-15-12 03.jpg
Menorah Manor 2-15-12 03.jpg 2012-02-15

SITEWORK

January 2012

Landscaping & Street Lights Installed.JPG
Landscaping & Street Lights Installed.JPG
Landscaping & Street Lights Installed.JPG 2012-01-20
Landscaping (1).JPG
Landscaping (1).JPG
Landscaping (1).JPG 2012-01-20
Landscaping (2).JPG
Landscaping (2).JPG
Landscaping (2).JPG 2012-01-29
Garden.JPG
Garden.JPG
Garden.JPG 2012-01-31
Walkway at Back of Building.JPG
Walkway at Back of Building.JPG
Walkway at Back of Building.JPG 2012-01-05
Gazebo.JPG
Gazebo.JPG
Gazebo.JPG 2012-01-29
Paving the Parking Lot (1).JPG
Paving the Parking Lot (1).JPG
Paving the Parking Lot (1).JPG 2012-01-13
Paving the Parking Lot (2).JPG
Paving the Parking Lot (2).JPG
Paving the Parking Lot (2).JPG 2012-01-17

December 2011

Landscaping Begins.JPG
Landscaping Begins.JPG
Landscaping Begins.JPG 2011-12-29
Back Porch Prep.JPG
Back Porch Prep.JPG
Back Porch Prep.JPG 2011-12-14
Forming Cantilever for Promenade.JPG
Forming Cantilever for Promenade.JPG
Forming Cantilever for Promenade.JPG 2011-12-14
Promenade Sidewalk Layout.JPG
Promenade Sidewalk Layout.JPG
Promenade Sidewalk Layout.JPG 2011-12-28
Gazebo Concrete.JPG
Gazebo Concrete.JPG
Gazebo Concrete.JPG 2011-12-15
Gazebo & Sidewalk Concrete.JPG
Gazebo & Sidewalk Concrete.JPG
Gazebo & Sidewalk Concrete.JPG 2011-12-20
Promenade Layout.JPG
Promenade Layout.JPG
Promenade Layout.JPG 2011-12-05
Promenade Concrete Pour.JPG
Promenade Concrete Pour.JPG
Promenade Concrete Pour.JPG 2011-12-21
Promenade Finished Concrete (1).JPG
Promenade Finished Concrete (1).JPG
Promenade Finished Concrete (1).JPG 2011-12-21
Promenade Finished Concrete (2).JPG
Promenade Finished Concrete (2).JPG
Promenade Finished Concrete (2).JPG 2011-12-28
South Parking Lot (1).JPG
South Parking Lot (1).JPG
South Parking Lot (1).JPG 2011-12-21
South Parking Lot (2).JPG
South Parking Lot (2).JPG
South Parking Lot (2).JPG 2011-12-15
South Parking Lot (3).JPG
South Parking Lot (3).JPG
South Parking Lot (3).JPG 2011-12-15

November 2011

Promenade Preparation
Promenade Preparation
IMGP1801.JPG 2011-11-18
Promenade Layout
Promenade Layout
IMGP1805.JPG 2011-11-22
Promenade Layout
Promenade Layout
IMGP1920.JPG 2011-12-01
Promenade Layout
Promenade Layout
IMGP1922.JPG 2011-12-01
Progress Energy Laying Conduit
Progress Energy Laying Conduit
IMGP1829.JPG 2011-11-22
Swimming Pool Prep
Swimming Pool Prep
IMGP1698.JPG 2011-11-03
Swimming Pool Poured
Swimming Pool Poured
IMGP1756.JPG 2011-11-10

Sitework

Virginia Avenue Sidewalk
Virginia Avenue Sidewalk

Virginia Avenue Underground Pipe
Virginia Avenue Underground Pipe







Area 'A' foundation layout with pond
Area 'A' foundation layout with pond

Grading after storm drainage has been installed
Grading after storm drainage has been installed

Overall slab view
Overall slab view

Grading the rest of the slab
Grading the rest of the slab

Storm pipe entering catch basin
Storm pipe entering catch basin

IMGP0005.JPG
IMGP0005.JPG

Storm Pipe and Catch Basin
Storm Pipe and Catch Basin

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Jan 2011 Sitework
Jan 2011 Sitework

Donor Wall

Donor Wall

Donor Wall (6).JPG
Donor Wall (6).JPG
Donor Wall (6).JPG 2011-12-13
Donor Wall (2).JPG
Donor Wall (2).JPG
Donor Wall (2).JPG 2011-12-06
Donor Wall (1).JPG
Donor Wall (1).JPG
Donor Wall (1).JPG 2011-12-06
Donor Wall (3).JPG
Donor Wall (3).JPG
Donor Wall (3).JPG 2011-12-06
Donor Wall (4).JPG
Donor Wall (4).JPG
Donor Wall (4).JPG 2011-12-06
Donor Wall (5).JPG
Donor Wall (5).JPG
Donor Wall (5).JPG 2011-12-13

Model Apartments

Memory Care Apartment

IMGP1481.JPG
IMGP1481.JPG
IMGP1481.JPG 2011-09-28
IMGP1482.JPG
IMGP1482.JPG
IMGP1482.JPG 2011-09-28
IMGP1483.JPG
IMGP1483.JPG
IMGP1483.JPG 2011-09-28
IMGP1485.JPG
IMGP1485.JPG
IMGP1485.JPG 2011-09-28

Residential Apartment

IMGP1479.JPG
IMGP1479.JPG
IMGP1479.JPG 2011-09-28
IMGP1475.JPG
IMGP1475.JPG
IMGP1475.JPG 2011-09-28
IMGP1471.JPG
IMGP1471.JPG
IMGP1471.JPG 2011-09-28
IMGP1470.JPG
IMGP1470.JPG
IMGP1470.JPG 2011-09-28

MEMORY CARE

January 2012

Memory Support Bedroom.JPG
Memory Support Bedroom.JPG
Memory Support Bedroom.JPG 2012-01-31
Memory Support Bathroom.JPG
Memory Support Bathroom.JPG
Memory Support Bathroom.JPG 2012-01-30
Memory Support Living Room.JPG
Memory Support Living Room.JPG
Memory Support Living Room.JPG 2012-01-30
Memory Support Dining.JPG
Memory Support Dining.JPG
Memory Support Dining.JPG 2012-01-31
Memory Support Food Service.JPG
Memory Support Food Service.JPG
Memory Support Food Service.JPG 2012-01-31
Memory Support Bath.JPG
Memory Support Bath.JPG
Memory Support Bath.JPG 2012-01-31

December 2011

1st Floor Resident Unit.JPG
1st Floor Resident Unit.JPG
1st Floor Resident Unit.JPG 2011-12-29
1st Floor Resident Bathroom.JPG
1st Floor Resident Bathroom.JPG
1st Floor Resident Bathroom.JPG 2011-12-29
1st Floor Living Room.JPG
1st Floor Living Room.JPG
1st Floor Living Room.JPG 2011-12-28
Dining Area Floor Prep.JPG
Dining Area Floor Prep.JPG
Dining Area Floor Prep.JPG 2011-12-01
Dining Area Cabinetry.JPG
Dining Area Cabinetry.JPG
Dining Area Cabinetry.JPG 2011-12-28
1st Floor Shower Room.JPG
1st Floor Shower Room.JPG
1st Floor Shower Room.JPG 2011-12-29
2nd Floor Resident Bathroom.JPG
2nd Floor Resident Bathroom.JPG
2nd Floor Resident Bathroom.JPG 2011-12-29
3rd Floor Lounge.JPG
3rd Floor Lounge.JPG
3rd Floor Lounge.JPG 2011-12-29

November 2011

1st Floor Living Unit
1st Floor Living Unit
IMGP1928.JPG 2011-12-01
1st Floor
1st Floor
IMGP1864.JPG 2011-11-29
1st Floor Living Room
1st Floor Living Room
IMGP1927.JPG 2011-12-01
Food Service
Food Service
IMGP1870.JPG 2011-11-29
Dining Area Floor Prep
Dining Area Floor Prep
IMGP1915.JPG 2011-12-01
2nd Floor Corridor
2nd Floor Corridor
IMGP1858.JPG 2011-11-29
2nd Floor Bathroom
2nd Floor Bathroom
IMGP1859.JPG 2011-11-29
2nd Floor Cabinetry
2nd Floor Cabinetry
IMGP1860.JPG 2011-11-29
3rd Floor Bathroom
3rd Floor Bathroom
IMGP1853.JPG 2011-11-29
3rd Floor Unit Drywall
3rd Floor Unit Drywall
IMGP1854.JPG 2011-11-29
3rd Floor Corridor
3rd Floor Corridor
IMGP1857.JPG 2011-11-29

October 2011

Memory Care Exterior
Memory Care Exterior
IMGP1554.JPG 2011-10-06
1st Floor Living Units Paint/Tile
1st Floor Living Units Paint/Tile
IMGP1677.JPG 2011-10-27
1st Floor Living Room Area
1st Floor Living Room Area
IMGP1615.JPG 2011-10-25
1st Floor Common Area
1st Floor Common Area
IMGP1617.JPG 2011-10-25
2nd Floor Corridor
2nd Floor Corridor
IMGP1621.JPG 2011-10-25
2nd Floor Living Room Area
2nd Floor Living Room Area
IMGP1622.JPG 2011-10-25
2nd Floor Common Area
2nd Floor Common Area
IMGP1623.JPG 2011-10-25
3rd Floor Corridor
3rd Floor Corridor
IMGP1624.JPG 2011-10-25
3rd Floor Living Units
3rd Floor Living Units
IMGP1625.JPG 2011-10-25
3rd Floor Common Area
3rd Floor Common Area
IMGP1629.JPG 2011-10-25

September 2011

IMGP1533.JPG
IMGP1533.JPG
IMGP1533.JPG 2011-09-28
IMGP1395.JPG
IMGP1395.JPG
IMGP1395.JPG 2011-09-15
IMGP1493.JPG
IMGP1493.JPG
IMGP1493.JPG 2011-09-28
IMGP1496.JPG
IMGP1496.JPG
IMGP1496.JPG 2011-09-28
IMGP1492.JPG
IMGP1492.JPG
IMGP1492.JPG 2011-09-28
IMGP1501.JPG
IMGP1501.JPG
IMGP1501.JPG 2011-09-28
IMGP1500.JPG
IMGP1500.JPG
IMGP1500.JPG 2011-09-28
IMGP1498.JPG
IMGP1498.JPG
IMGP1498.JPG 2011-09-28

August 2011

Roof Trusses/Scaffolding
Roof Trusses/Scaffolding

Scaffolding for Stucco Application
Scaffolding for Stucco Application

Stucco Application
Stucco Application

Painting Begins
Painting Begins

3rd Floor Paint/Windows
3rd Floor Paint/Windows

1st Floor Unit
1st Floor Unit

2nd Floor Layout
2nd Floor Layout

3rd Floor Layout
3rd Floor Layout

July 2011



Scaffolding for Stucco Work


Window Prep for Scaffolding


1st Floor Layout/Rough-In


3rd Floor Layout/Rough-In


2nd Floor Layout/Rough-In


Stairs Are In!




Swinging Trusses to Roof


Crane Swinging Trusses


Roof Trusses/Plywood


Installed Trusses


View of Trusses from Ground Level

June 2011

3rd Floor Concrete Topping
3rd Floor Concrete Topping

1st Floor Metal Framing and Fire Sprinkler Layout
1st Floor Metal Framing and Fire Sprinkler Layout

1st Floor Wall Layout
1st Floor Wall Layout

2nd Floor Wall Layout
2nd Floor Wall Layout

3 Story Memory Care Side View
3 Story Memory Care Side View

Memory Care 3rd Floor Block Work
Memory Care 3rd Floor Block Work

May, 2011

IMGP0299.JPG
IMGP0299.JPG
IMGP0299.JPG 2011-05-04
IMGP0300.JPG
IMGP0300.JPG
IMGP0300.JPG 2011-05-04
IMGP0276.JPG
IMGP0276.JPG
IMGP0276.JPG 2011-05-04
IMGP0314.JPG
IMGP0314.JPG
IMGP0314.JPG 2011-05-09
IMGP0355.JPG
IMGP0355.JPG
IMGP0355.JPG 2011-05-13
IMGP0358.JPG
IMGP0358.JPG
IMGP0358.JPG 2011-05-13
IMGP0487.JPG
IMGP0487.JPG
IMGP0487.JPG
IMGP0447.JPG
IMGP0447.JPG
IMGP0447.JPG 2011-05-27
IMGP0452.JPG
IMGP0452.JPG
IMGP0452.JPG 2011-05-27

Going Vertical































Slab Pour




























IMGP0126.JPG
IMGP0126.JPG
IMGP0126.JPG 2011-04-07

Foundations




























RESIDENTIAL UNITS

January 2012

Exterior Landscaping.JPG
Exterior Landscaping.JPG
Exterior Landscaping.JPG 2012-01-29
Entry & Kitchen (1 & 2 Bedroom Units).JPG
Entry & Kitchen (1 & 2 Bedroom Units).JPG
Entry & Kitchen (1 & 2 Bedroom Units).JPG 2012-01-30
Living Room.JPG
Living Room.JPG
Living Room.JPG 2012-01-20
Bathroom.JPG
Bathroom.JPG
Bathroom.JPG 2012-01-30
Studio Unit.JPG
Studio Unit.JPG
Studio Unit.JPG 2012-01-31
Entry & Kitchen (Studio Unit).JPG
Entry & Kitchen (Studio Unit).JPG
Entry & Kitchen (Studio Unit).JPG 2012-01-30
Handicap Bathroom.JPG
Handicap Bathroom.JPG
Handicap Bathroom.JPG 2012-01-30

December 2011

Resident Room.JPG
Resident Room.JPG
Resident Room.JPG 2011-12-29
Resident Room Carpet Installation.JPG
Resident Room Carpet Installation.JPG
Resident Room Carpet Installation.JPG 2011-12-28
Resident Bathroom.JPG
Resident Bathroom.JPG
Resident Bathroom.JPG 2011-12-28
3rd Floor Corridor Ceiling Grid.JPG
3rd Floor Corridor Ceiling Grid.JPG
3rd Floor Corridor Ceiling Grid.JPG 2011-12-28
3rd Floor Lounge Area.JPG
3rd Floor Lounge Area.JPG
3rd Floor Lounge Area.JPG 2011-12-29
Laundry Room.JPG
Laundry Room.JPG
Laundry Room.JPG 2011-12-28
Elevator Start Up.JPG
Elevator Start Up.JPG
Elevator Start Up.JPG 2011-12-28

November 2011

1st Floor Cabinetry
1st Floor Cabinetry
IMGP1834.JPG 2011-11-29
1st Floor Bath
1st Floor Bath
IMGP1838.JPG 2011-11-29
1st Floor Corridors
1st Floor Corridors
IMGP1907.JPG 2011-12-01
2nd Floor Bath
2nd Floor Bath
IMGP1910.JPG 2011-12-01
2nd Floor Living Unit
2nd Floor Living Unit
IMGP1911.JPG 2011-12-01
2nd Floor Living Unit
2nd Floor Living Unit
IMGP1844.JPG 2011-11-29
2nd Floor Common Area
2nd Floor Common Area
IMGP1850.JPG 2011-11-29
2nd Floor Corridors
2nd Floor Corridors
IMGP1841.JPG 2011-11-29
3rd Floor Living Unit
3rd Floor Living Unit
IMGP1847.JPG 2011-11-29
3rd Floor Bath
3rd Floor Bath
IMGP1848.JPG 2011-11-29
3rd Floor Corridors
3rd Floor Corridors
IMGP1846.JPG 2011-11-29

October 2011

Resident Units Exterior View
Resident Units Exterior View
IMGP1691.JPG 2011-10-27
1st Floor Common Area
1st Floor Common Area
IMGP1646.JPG 2011-10-25
1st Floor Living Area
1st Floor Living Area
IMGP1647.JPG 2011-10-25
1st Floor Corridor
1st Floor Corridor
IMGP1648.JPG 2011-10-25
2nd Floor Common Area
2nd Floor Common Area
IMGP1649.JPG 2011-10-25
2nd Floor Living Area
2nd Floor Living Area
IMGP1650.JPG 2011-10-25
3rd Floor Common Area
3rd Floor Common Area
IMGP1653.JPG 2011-10-25
3rd Floor Living Area
3rd Floor Living Area
IMGP1652.JPG 2011-10-25
3rd Floor Corridor
3rd Floor Corridor
IMGP1651.JPG 2011-10-25

September 2011

IMGP1512.JPG
IMGP1512.JPG
IMGP1512.JPG 2011-09-28
IMGP1507.JPG
IMGP1507.JPG
IMGP1507.JPG 2011-09-28
IMGP1506.JPG
IMGP1506.JPG
IMGP1506.JPG 2011-09-28

August 2011

Hollowcore Roof Planks
Hollowcore Roof Planks

Roof Trusses
Roof Trusses

1st Floor Room Layout
1st Floor Room Layout

2nd Floor Room Layout
2nd Floor Room Layout

3rd Floor Room Layouot
3rd Floor Room Layouot

July 2011



3rd Floor Block Work


IMGP1011.JPG
IMGP1011.JPG
IMGP1011.JPG 2011-07-29


3rd Floor Steel


3rd Floor Ready for Hollow Core Planks
IMGP0986.JPG
IMGP0986.JPG
IMGP0986.JPG 2011-07-29


1st Floor Layout/Rough-In

June 2011

2nd Floor Block Work
2nd Floor Block Work

1st Floor Room Layout
1st Floor Room Layout

Setting Steel
Setting Steel
IMGP0643.JPG 2011-06-21
1st & 2nd Floor Block Walls
1st & 2nd Floor Block Walls

1st & 2nd Floor Block Walls
1st & 2nd Floor Block Walls

May 2011

IMGP0324.JPG
IMGP0324.JPG
IMGP0324.JPG 2011-05-10
IMGP0374.JPG
IMGP0374.JPG
IMGP0374.JPG 2011-05-17
IMGP0377.JPG
IMGP0377.JPG
IMGP0377.JPG 2011-05-17
IMGP0402.JPG
IMGP0402.JPG
IMGP0402.JPG 2011-05-18
IMGP0414.JPG
IMGP0414.JPG
IMGP0414.JPG 2011-05-18
IMGP0423.JPG
IMGP0423.JPG
IMGP0423.JPG 2011-05-26
IMGP0427.JPG
IMGP0427.JPG
IMGP0427.JPG 2011-05-26
IMGP0473.JPG
IMGP0473.JPG
IMGP0473.JPG 2011-05-27
IMGP0338.JPG
IMGP0338.JPG
IMGP0338.JPG 2011-05-12
IMGP0482.JPG
IMGP0482.JPG
IMGP0482.JPG

Slab Pour













IMGP0239.JPG
IMGP0239.JPG

Foundations



















IMGP0100.JPG
IMGP0100.JPG
IMGP0100.JPG 2011-04-04
IMGP0101.JPG
IMGP0101.JPG
IMGP0101.JPG 2011-04-04
IMGP0106.JPG
IMGP0106.JPG
IMGP0106.JPG 2011-04-04

MULTI PURPOSE/KITCHEN, ADMINISTRATION, & ASSEMBLY

January 2012

Main Entrance.JPG
Main Entrance.JPG
Main Entrance.JPG 2012-01-29
Assembly.JPG
Assembly.JPG
Assembly.JPG 2012-01-25
2nd Floor View of Main Dining.JPG
2nd Floor View of Main Dining.JPG
2nd Floor View of Main Dining.JPG 2012-01-30
Dining Room Flooring.JPG
Dining Room Flooring.JPG
Dining Room Flooring.JPG 2012-01-12
Multi-Purpose Room.JPG
Multi-Purpose Room.JPG
Multi-Purpose Room.JPG 2012-01-31
Private Dining.JPG
Private Dining.JPG
Private Dining.JPG 2012-01-30
Ready to Hook Up Kitchen Equipment.JPG
Ready to Hook Up Kitchen Equipment.JPG
Ready to Hook Up Kitchen Equipment.JPG 2012-01-30

December 2011

Front Entry.JPG
Front Entry.JPG
Front Entry.JPG 2011-12-28
Assembly Drywall Finishers.JPG
Assembly Drywall Finishers.JPG
Assembly Drywall Finishers.JPG 2011-12-28
2nd Floor Open to Dining.JPG
2nd Floor Open to Dining.JPG
2nd Floor Open to Dining.JPG 2011-12-28
Cooking Studio.JPG
Cooking Studio.JPG
Cooking Studio.JPG 2011-12-28
Kitchen 1.JPG
Kitchen 1.JPG
Kitchen 1.JPG 2011-12-28
Kitchen 2.JPG
Kitchen 2.JPG
Kitchen 2.JPG 2011-12-28
Kitchen 3.JPG
Kitchen 3.JPG
Kitchen 3.JPG 2011-12-28
Kitchen 4.JPG
Kitchen 4.JPG
Kitchen 4.JPG 2011-12-28
Pool Wall 1.JPG
Pool Wall 1.JPG
Pool Wall 1.JPG 2011-12-15
Pool Wall 2.JPG
Pool Wall 2.JPG
Pool Wall 2.JPG 2011-12-28

November 2011

Kitchen Flooring Installed
Kitchen Flooring Installed
IMGP1739.JPG 2011-11-09
Lobby/Assembly
Lobby/Assembly
IMGP1761.JPG 2011-11-10
Multipurpose Room Ceiling Grid
Multipurpose Room Ceiling Grid
IMGP1803.JPG 2011-11-18
Folding Partition Wall
Folding Partition Wall
IMGP1878.JPG 2011-11-29
Laundry Equipment Arrived
Laundry Equipment Arrived
IMGP1935.JPG 2011-12-01

October 2011

Back Entrance Prepped for Stucco/Paint
Back Entrance Prepped for Stucco/Paint
IMGP1671.JPG 2011-10-25
Administration Exterior Prepped for Stucco and Roofing
Administration Exterior Prepped for Stucco and Roofing
IMGP1658.JPG 2011-10-25
Exterior Multipurpose Room Prepped for Stucco
Exterior Multipurpose Room Prepped for Stucco
IMGP1657.JPG 2011-10-25
Porte Cochere
Porte Cochere
IMGP1683.JPG 2011-10-27
Multipurpose Room
Multipurpose Room
IMGP1640.JPG 2011-10-25
Assembly Area
Assembly Area
IMGP1663.JPG 2011-10-25
Dining Area Ceiling Installation
Dining Area Ceiling Installation
IMGP1571.JPG 2011-10-12
Dining Area Finished Ceiling
Dining Area Finished Ceiling
IMGP1635.JPG 2011-10-25
Public Restroom Ceramic Tile Installation
Public Restroom Ceramic Tile Installation
IMGP1659.JPG 2011-10-25

September 2011

IMGP1489.JPG
IMGP1489.JPG
IMGP1489.JPG 2011-09-28
IMGP1513.JPG
IMGP1513.JPG
IMGP1513.JPG 2011-09-28
IMGP1514.JPG
IMGP1514.JPG
IMGP1514.JPG 2011-09-28
IMGP1520.JPG
IMGP1520.JPG
IMGP1520.JPG 2011-09-28
IMGP1518.JPG
IMGP1518.JPG
IMGP1518.JPG 2011-09-28
IMGP1374.JPG
IMGP1374.JPG
IMGP1374.JPG 2011-09-13
IMGP1451.JPG
IMGP1451.JPG
IMGP1451.JPG 2011-09-21
IMGP1530.JPG
IMGP1530.JPG
IMGP1530.JPG 2011-09-28

August 2011

Porte Cochere / Front Entrance
Porte Cochere / Front Entrance

Assembly Roof Trusses
Assembly Roof Trusses

Door Installation Begins
Door Installation Begins

Air Handler Units
Air Handler Units

Air Handler Units
Air Handler Units

Storefront Windows
Storefront Windows

2nd Floor Windows
2nd Floor Windows

Multipurpose Room
Multipurpose Room

Multipurpose Room Windows
Multipurpose Room Windows

Cooler / Freezer
Cooler / Freezer

Administration Interior Framing
Administration Interior Framing

Mechanical Yard
Mechanical Yard

July 2011



Administration Wall Framing


Administration Styrofoam for Roof Insulation


Administration Lightweight Concrete Insulation


Assembly Sprayed On Fireproofing


Assembly Fireproofing


Multi-Purpose Lightweight Concrete Roof Insulation
IMGP0921.JPG
IMGP0921.JPG
IMGP0921.JPG 2011-07-26


Administration Layout/Rough-In


Multi-Purpose HVAC Ductwork


Column Frames for Porte Cochure

June 2011

Multi-Purpose Block Work
Multi-Purpose Block Work

Multi-Purpose Block/Steel
Multi-Purpose Block/Steel

Multi-Purpose Building Side View
Multi-Purpose Building Side View
IMGP0543.JPG 2011-06-09
Inn on the Pond Entrance
Inn on the Pond Entrance

Administration Foundation
Administration Foundation

Administration Building Block Work
Administration Building Block Work

Administration Interior
Administration Interior
IMGP0702.JPG 2011-07-05

May 2011

IMGP0321.JPG
IMGP0321.JPG
IMGP0321.JPG 2011-05-10
IMGP0325.JPG
IMGP0325.JPG
IMGP0325.JPG 2011-05-10
IMGP0339.JPG
IMGP0339.JPG
IMGP0339.JPG 2011-05-12
IMGP0440.JPG
IMGP0440.JPG
IMGP0440.JPG 2011-05-27
IMGP0454.JPG
IMGP0454.JPG
IMGP0454.JPG 2011-05-27
IMGP0416.JPG
IMGP0416.JPG
IMGP0416.JPG 2011-05-19
IMGP0456.JPG
IMGP0456.JPG
IMGP0456.JPG 2011-05-27
IMGP0484.JPG
IMGP0484.JPG
IMGP0484.JPG

"ZERO PUNCH"

If you visit our job site these days, you may notice signs posted throughout the building proclaiming "Zero Punch".  "Zero Punch" is a quality initiative started by Creative Contractors to reduce the size of punch lists.  The objective is to be defect-free in construction and deliver a completed building to the owner sooner, without any call-backs.

 

For those unfamiliar with the term punch list, McGraw-Hill defines the term as "a checklist of all items on a construction project that are unfinished or incomplete, have not been done at all, require replacement or repair, or require additional work to achieve an acceptable level of workmanship”.

 

Creative Contractors believes that attention to quality and detail starts from the first day on the job.  Under the “Zero Punch” approach, subcontractors are encouraged to check their work daily, and check again as they leave each finished area, resulting in minimal punch lists at the end of the project.  Minimal punch lists lead to a quicker closeout of the construction phase of the project, and a smooth transition for the new owners.


Our Subcontractors

A-Plus Fireplaces, Granite & Marble
Acousti Engineering Co. of Florida
Apex Pest Control
APG Electric, Inc.
Awning Works, Inc.
B.R.W. Contracting, Inc.
Bay Area Commercial Interiors
Bayshore Plumbing, Inc.
Blume Mechanical
Coreslab Structures, Inc.
Countryside Glass & Mirror
Craft Equipment Company
Curtis Pools
East Coast Applicators, Inc.
Economy Caulking
Gilbert & Byrd Masonry, Inc.
Gravity-Ratterman, LLC
Harrison/Pacific, LLC
Hile's Curtain Specialties
Horizon Surface Systems
Hufcor Florida Group
J&E Custom Fabricators, Inc.
KHS&S Contractors
Otis Elevator Company
Overhead Door Co. of Tampa
Peterson Metals
Pinnacle Door & Hardware, Inc.
Pro-Crete Systems, Inc.
Ramcon, LLC
Southern Quality, Inc.
St. Petersburg Fire Protection LLC
Sunshine Services of Central Florida
Tailored Foam of Florida, Inc.
Trio Plus Painting, Inc.
United Steel Works, Inc.
ValleyCrest Landscape Development

 

 


Topping Out Party - July 21, 2011

IMGP0856.JPG
IMGP0856.JPG
IMGP0856.JPG 2011-07-21
IMGP0854.JPG
IMGP0854.JPG
IMGP0854.JPG 2011-07-21
IMGP0844.JPG
IMGP0844.JPG
IMGP0844.JPG 2011-07-21
IMGP0847.JPG
IMGP0847.JPG
IMGP0847.JPG 2011-07-21
IMGP0860.JPG
IMGP0860.JPG
IMGP0860.JPG 2011-07-21
IMGP0841.JPG
IMGP0841.JPG
IMGP0841.JPG 2011-07-21
IMGP0846.JPG
IMGP0846.JPG
IMGP0846.JPG 2011-07-21
IMGP0850.JPG
IMGP0850.JPG
IMGP0850.JPG 2011-07-21
IMGP0858.JPG
IMGP0858.JPG
IMGP0858.JPG 2011-07-21
IMGP0855.JPG
IMGP0855.JPG
IMGP0855.JPG 2011-07-21
IMGP0859.JPG
IMGP0859.JPG
IMGP0859.JPG 2011-07-21
IMGP0870.JPG
IMGP0870.JPG
IMGP0870.JPG 2011-07-21
IMGP0874.JPG
IMGP0874.JPG
IMGP0874.JPG 2011-07-21

The Inn on the Pond

A Tour of The Inn on the Pond

Inn on the Pond Monument Sign
Inn on the Pond Monument Sign
IMGP2816.JPG 2012-04-11
Front Entry
Front Entry
IMGP2819.JPG 2012-04-11
Front Entry
Front Entry
IMGP2821.JPG 2012-04-11


IMGP2823.JPG 2012-04-11
Front Pool Area
Front Pool Area
IMGP2717.JPG 2012-03-01
Swimming Pool
Swimming Pool
IMGP2729.JPG 2012-03-01
Pool Bath
Pool Bath
IMGP2672.JPG 2012-02-27
Promenade
Promenade
IMGP2626.JPG 2012-02-21
Promenade
Promenade
IMGP2757.JPG 2012-03-06
Patio/Promenade
Patio/Promenade
IMGP2771.JPG 2012-03-08
Patio
Patio
IMGP2756.JPG 2012-03-06
Gazebo
Gazebo
IMGP2775.JPG 2012-03-08
Third Floor View of the Pond
Third Floor View of the Pond
IMGP2790.JPG 2012-03-08
Assembly
Assembly
IMGP2663.JPG 2012-02-24
Concierge Desk
Concierge Desk
IMGP2735.JPG 2012-03-06
Multi-Purpose Room
Multi-Purpose Room
IMGP2794.JPG 2012-03-14
Bistro
Bistro
IMGP2732.JPG 2012-03-01
Bistro
Bistro
IMGP2797.JPG 2012-03-14
Library
Library
IMGP2798.JPG 2012-03-14
Dining Area
Dining Area
IMGP2799.JPG 2012-03-14
Private Dining
Private Dining
IMGP2778.JPG 2012-03-08
Kitchen
Kitchen
IMGP2656.JPG 2012-02-24
IMGP2519.JPG
IMGP2519.JPG
IMGP2519.JPG 2012-02-02
Kitchen
Kitchen
IMGP2522.JPG 2012-02-02
Resident Room Living Room
Resident Room Living Room
IMGP1479.JPG 2011-09-28
Resident Room Kitchen/Dining
Resident Room Kitchen/Dining
IMGP1475.JPG 2011-09-28
Resident Room Bathroom
Resident Room Bathroom
IMGP1470.JPG 2011-09-28
Resident Room Shower
Resident Room Shower
IMGP1471.JPG 2011-09-28
Lounge
Lounge
IMGP2802.JPG 2012-03-14
Lounge
Lounge
IMGP2804.JPG 2012-03-14
Memory Care Room
Memory Care Room
IMGP1485.JPG 2011-09-28
Memory Care Bedroom
Memory Care Bedroom
IMGP1482.JPG 2011-09-28
Memory Care Bedroom
Memory Care Bedroom
IMGP1483.JPG 2011-09-28
Memory Care Patio
Memory Care Patio
IMGP2751.JPG 2012-03-06
Memory Care Garden
Memory Care Garden
IMGP2752.JPG 2012-03-06
Memory Care Garden
Memory Care Garden
IMGP2753.JPG 2012-03-06
Fitness Room
Fitness Room
IMGP2785.JPG 2012-03-08
Beauty Salon
Beauty Salon
IMGP2787.JPG 2012-03-08
Spa Tub
Spa Tub
IMGP2791.JPG 2012-03-08